ATCO Gas Australia have strict regulations for any work around high pressure infrastructure. All work within 15 meters needs to be approved by ATCO and any work within 5 meters requires an ATCO approved High Pressure gas supervisor. High Pressure gas supervisors have approval to act on ATCO’s behalf and will provide expert guidance for drilling contractors, excavations, installing signs or structures, hot works, vibration and compaction and dewatering.
Please use the contact form for any questions relating High Pressure gas locators from Pulse Locating.
In tougher ground conditions, medium to high pressure water can be used via a lance and suction pipe to cut through clays and road bases. Our potholing lances are designed to use pressure and suction at the same time to reduce mess and provide safety to our workers. Although medium to high water pressure may sound damaging to services, it is pivotal in locating pipes and cables as it significantly reduces the use of other digging tools such as shovels and crow bars which could cause extensive damage.